4. Risk Management Structure
The basic structure recommended for risk management consists of a Risk Manager
who is responsible for the definition, structure, implementation and coordination
of a risk management approach consistent with the program, system engineering,
test , manufacturing and verification plans. The risk manager works on the staff
of the program manager. The risk management job is comparable to that of Configuration
Manager, Data Manager, Program Management (PMS) and other staff level positions
that do not have a direct objective product development role.
It is the Risk Manager's job to coordinate the risk management activities within
the prime's organization and with all subcontractors. The Risk Manager assists
the Program Manager in the PM's role of Risk Board Chairman.
The Risk Manager schedules and oversees the production of all risk reviews,
either as stand alone events or as part of management reviews. This entails
alerting risk owners and risk board members of support requirements for such
reviews. The Risk Manager is responsible for preparing and distributing the
minutes from risk board meetings.
The risk manager is responsible for coordinating and presenting at least the
summary of risk management activities at all major reviews.
|
|